Written answer by Ministry of National Development on Estate Upgrading Programme for Jalan Naung and Realty Park private estates

Oct 14, 2025


Question No. 677

Question by: Mr Dennis Tan Lip Fong

Question  

To ask the Minister for National Development (a) following the Ministry's announcement in February 2025, when is the Estate Upgrading Programme for Jalan Naung and Realty Park private estates expected to commence within the next five years; and (b) what specific works will be undertaken for these estates.

Answer

The Estate Upgrading Programme (EUP) for Jalan Naung & Realty Park Estate is targeted to commence by the middle of 2026, starting with the design and planning of the project. BCA will call a tender by end 2025 to appoint the consultants. Enhancements under the EUP may include (i) recreational spaces such as community gardens, playgrounds and fitness corners; (ii) features to improve connectivity and accessibility such as footpaths, barrier-free ramps and wayfinding markers; and (iii) estate markers.