|
Safety
at Existing Deep Excavation Sites
2 First, I would like to reassure the
public about the safety of existing deep excavation
sites. Following the collapse of Nicoll Highway, BCA
asked LTA to suspend deep excavation works for all the
Circle Line sites, pending a comprehensive review of
the design and construction pertaining to deep excavation
at these sites. Work at these sites were progressively
released only after BCA was satisfied that the design
of temporary works and monitoring measures were adequate.
BCA continues to monitor closely the works at the Circle
Line sites, as well as other sites where deep excavation
works are being carried out.
3 Next, the COI has recommended that
a code of practice for deep excavation works be developed.
This is to provide guidance to designers and builders
on how to strengthen the design robustness and construction
of deep excavation works. MND supports this. A technical
committee under Spring Singapore, comprising members
from BCA, MOM, LTA, the universities and other practicing
professionals, is working on a Singapore Code on Deep
Excavation and hopes to get this ready soon.
4 While details of this Code are being
finalised, BCA has in the interim issued an advisory
note to the industry. This advisory is to set preliminary
standards for the design and construction of Temporary
Earth Retaining Structures (TERS) in deep excavation
works.
Joint
MND-MOM Construction Safety Review
5 Together with the Ministry for Manpower,
my Ministry set up a Joint Review Committee (JRC) about
a year ago to thoroughly review the regulatory framework
and practices of the construction industry, with the
aim of improving safety standards.
6 While the COI recommendations were
based on findings on the causes of the Nicoll Highway
collapse, the JRC reviewed the whole construction value
chain from design to procurement and construction, and
assessed the gaps and weaknesses in the system, taking
into account the human factor. In the course of its
work, the JRC also took into consideration the lessons
and findings from the COI inquiry.
7 These two investigations complement each other and
will ensure that our effort to strengthen the safety
regime in construction is thorough and comprehensive.
The JRC proposals will address all the COI recommendations.
JRC
Recommendations
Regulatory
Framework and Competence of Professionals
8 The COI pointed out that temporary
works pertaining to deep excavation were not regulated
to the same degree as permanent works. MND agrees with
this observation.
9 To enhance the regulation of deep
excavation works and ensure the competence of personnel
involved in such works, BCA will be implementing the
following measures, as recommended by the JRC:
- First, professional engineers (PE) who are specialists
in geotechnical engineering will be required to design
and supervise the Temporary Earth Retaining Structures
(TERS) in deep excavation.
- Second, PEs will be required to show proof that they
have attended accredited courses on critical design
codes and the software used in their building plan submissions.
- Third, supervision teams of engineers, in various
numbers and with stipulated years of professional experience
and qualification, will be required to supervise structural
works, depending on the size of the project.
Chain
of Command and Independence
10 The COI also highlighted the importance
of having a well-established chain of command, and independence
for the QP (Supervision) to perform his role free from
cost and time pressures.
11
Currently, the Building Control Act prohibits the QP
(Supervision) from being associated with the builder,
but not the developer. MND accepts the COI’s observation
that this gives rise to potential conflict of interest. I have asked BCA to follow up on the JRC’s recommendation
to review the usual relationships QPs have in the industry,
with the developer, project manager, and other parties
involved in a construction project, with a view to reinforce
the independence of the QP.
12 As another layer of independent checks
on the designs of TERS in deep excavation, BCA will
require Accredited Checkers (AC) specialised in geotechnical
engineering to review these designs. As with the ACs
for permanent works, these AC (Geotechnic) will have
to be appointed by the owner or client, not the builder.
13
I also agree with the JRC’s recommendations that
the Building Control Units (BCUs) of LTA, JTC and HDB
should be discontinued and their functions centralised
at BCA. BCA will rescind the authorisation granted to
the BCUs of LTA, HDB and JTC, and assume direct charge
for the regulation of the building projects of these
three statutory boards.
14
Since 1995, BCA had authorised the BCUs of LTA, JTC
and HDB to carry out building control functions for
projects under their respective purview. This arrangement
has enabled these statutory boards to have better control
over the implementation of their extensive development
and building programmes.
15 The BCUs have built up a pool of
competent professionals and established internal quality
control mechanisms to effectively regulate the projects
under their purview. However, as the statutory boards
take on multiple roles as developer, designer, contractor
and regulator, there is a need to remove any doubts
that BCU staff will undertake their work with impartiality
and independence, and to maintain public accountability
and confidence in the regulatory system. Furthermore,
the centralisation of building control functions at
BCA will improve the regulatory framework. For example,
there will then be only one authority who will oversee
works pertaining to deep excavation.
Corporate
Competency and Safety Considerations in Selection
16 My Ministry has also accepted other
JRC recommendations aimed at promoting corporate competency
and safety culture. These are being worked on by BCA.
17 One of the key recommendations is
to license builders (or contractors). We will require
all builders who wish to undertake works that need building
control approval to have a licence. In addition, specialist
contractors whose works have a high impact on safety
will also need a licence. Such specialist contractors
include those engaged in piling works, earth retaining
and ground-stabilisation works, and soil investigations
and instrumentation. To obtain a licence, the builder
must satisfy some principal considerations, including
a good safety records, adequate financial and technical
resources, and competent or qualified persons responsible
for the management of the firm and the construction
activities. These are aimed at raising the competency
of contractors.
18 Although the COI concluded that the
tender selection of the Nicoll Highway contract (C824)
was not a problem, it recommended that in tender evaluation,
some weightage should be given to the safety records
and culture of the bidder and its corporate competency.
The JRC has also recommended that the Government formalise
the safety considerations in its procurement system
for construction works. It recommended the adoption
of a Price-Quality Method (PQM) for tender evaluation
that the BCA developed, which will mandate the use of
both price and quality attributes, with safety as a
mandatory quality attribute. The Government has accepted
this JRC recommendation.
Conclusion
19 In conclusion, I would like to reiterate
that my Ministry is committed to ensuring construction
safety. The measures proposed by JRC, when implemented,
will strengthen the regulatory framework and raise safety
standards and professionalism and competency in the
industry.
20 I want to urge everyone involved
– developers, professionals, contractors, workers
etc, to support and work closely with the various authorities
to evolve a safety culture that permeates throughout
the construction value chain. We must all be mindful
of our roles and responsibilities and the consequences
of our actions on construction safety. Let’s work
together, because precious lives are at stake.
>>back
to top
|